On Monday June 4th all of the necessary pre-construction requirements for Coal Creek Parkway have been met and the City has officially begun soliciting for construction bids on the project. Construction companies will now have until July 3rd to submit construction bid proposals. After that date the city will have 45 days in which to review the bid submissions and potentially award a contract to a bidder. If the bid proposals are within a reasonable range of the anticipated budget, the council will most likely award a contract well before the 45 day window is expired. At which point the construction will begin on Coal Creek Parkway. Construction is anticipated to last two years which would put the completion date sometime around mid-to-late 2009.